What is a Water
Reclaimation Facility?

How Can I Get Involved?

Project Documents

Past PDT Meetings
and Minutes

Policy Advisory Commitee (PAC)

Project Schedule

Related Links

Glossary

Who are the Partners?

 

 

Report PAC09-28

Report to the Policy Advisory Committee (PAC09-28)

Date:               March 5, 2009
To:                   Policy Advisory Committee
From:              Steve Brown, P.E. – Town of Cary, Director of Public Works and Utilities
Prepared By:   Leila Goodwin, P.E. – Town of Cary, Water Resources Manage
Subject:           Western Wake Regional Wastewater Facilities Budget Update and Proposed FY10 Operating Budget

Background

Section 3.3 of the “Design, Construction, Ownership, Management and Operation Agreement” dated August 22, 2005 (“Implementation Agreement”), specifies that:

“The Lead Agency shall prepare the Annual Budget for each Fiscal Year and as expeditiously as possible shall provide each of the Project Partners with the Annual Budget. The Lead Agency shall endeavor to prepare and provide to each Project Partner by each March 15 a preliminary Annual Budget for the ensuing Fiscal Year.  To the extent possible, the Lead Agency shall prepare the Annual Budget so that it will be possible to determine from such budget the Current Expenses for the Wastewater Management Facilities that will be allocable to each Project Partner during the Fiscal Year.”

Discussion

The Project Partners entered into two agreements specifying tasks to be undertaken by the Lead Agency, how costs for those tasks will be allocated, and anticipated budgets:

  • The Interlocal Agreement for Regional Wastewater Management Facilities Land Acquisition and Preliminary Work, as amended (“Preliminary Work Agreement”), addressed purchase of land for the Water Reclamation Facility (WRF) and pump stations; permitting; and organizational, institutional and financial development.  For budget discussion purposes, land costs will be included in facility design and construction costs.
  • The Agreement For Design, Construction, Ownership, Management And Operation Of Western Wake Regional Wastewater Management Facilities, as amended(Implementation Agreement), addressed design and construction of the facilities, and defined Fixed Current Expenses, which includes project management expenses before facility startup.

 

Report PAC07-10 dated February 15, 2007 presented several potential cost allocations for implementation of the Apex/Site 14 Water and Sewer Extension Policy and although Option 1 was selected by the Policy Advisory Committee at that time and is used in this update for discussion purposes, the Policy Advisory Committee subsequently agreed to revisit the cost allocations for this item.   The Lead Agency proposes bringing this item back to the Policy Advisory Committee after a Record of Decision is issued on the Environmental Impact Statement (expected late summer 2009).

Table 1 presents the cost shares for various components of the facilities. 

Preliminary Work
The Preliminary Work included two items: permitting; and organizational, institutional and financial development.    Table 2 shows a summary of the updated preliminary work budget.  Additional funding over what was reported last year (PAC08-23) is included for planning and permitting related to the potential for a discharge to Harris Lake (PAC09-29). A portion of the permitting cost has been reimbursed from a State Revolving Fund (SRF) loan, for which repayment has already begun.

We anticipate that some of the unspent funds budgeted for the organizational, institutional and financial development will be needed to finalize the service agreements between the Lead Agency and each partner; therefore, the budget for that item remains unchanged.  

Land Acquisition, Design and Construction
Costs have been updated based on the ongoing design of the facilities and increased knowledge of pipeline routes and potential easement costs.   

Summary of Capital Costs
Table 3 presents the updated cost estimates for land acquisition and facilities.  Table 4 presents a comparison of updated costs with the previously budgeted costs, by Partner.  Note that total costs have increased by about 7% since March 2008 due in part to:

  • Addition of compensatory mitigation costs for environmental impacts;
  • Addition of rock excavation costs and length to some of the larger pipelines based on more detailed information from soil boring tests;
  • Provision of an alternate solution for the manual bar rack at West Cary Pump Station that includes a comminutor;
  • Increased costs for the pumps at Beaver Creek and West Cary pump stations.
  • Addition of lab equipment in the estimates for the WRF;
  • Increased commodity costs for ductile iron, steel and stainless steel; and
  • Addition of a second mechanical screen for the Beaver Creek Pump Station in lieu of a manual bar rack.

Project Management
As has been discussed previously, there are operating expenses before startup of the facilities which are being billed to the Project Partners by the Lead Agency as Fixed Current Expenses.  To date these include salary costs for a project manager, contract costs for land acquisition services, and the cost for the annual audit. 

FY09 and Future Year Cash Flow Estimates
Table 5 presents an estimate of the timing of cash flow for the project, for each Project Partner.  The cash flow estimates shown in Table 5 incorporate the use and repayment of the SRF loan of about $4 million received for planning and permitting (including some design).   Table 6 shows the proposed FY09 Operating Budget broken down into permitting, capital, and project management costs. 

Requested Action:  The Technical Advisory Committee requests that the Policy Advisory Committee accept the recommended FY10 Operating Budget.


Table 1

Cost Share Allocations for Western Wake Regional Wastewater Management Facilities

Project Component

Apex

Cary

Holly Springs

Morrisville

Preliminary Work and Land Acquisition Agreement

Preliminary Work (Permitting)

26.9%

44.3%

22.5%

6.3%

Organizational, Financial, Institutional

26.9%

44.3%

22.5%

6.3%

West Cary PS Land

0%

87.5%

0%

12.5%

Beaver Creek PS Land

34.7%

57.2%

0%

8.1%

Western Wake WRF Land

34.7%

57.2%

0%

8.1%

Effluent Pump Station Land

26.9%

44.3%

22.5%

6.3%

Design, Construction, Ownership, Management And Operation Agreement

West Cary PS

0%

87.8%

0%

12.2%

West Cary Force Main

0%

87.8%

0%

12.2%

West Cary Force Main Land

0%

87.5%

0%

12.5%

West Reedy Branch Gravity Sewer

9.3%

78.7%

0%

12.0%

West Reedy Branch Gravity Sewer Land

10.6%

78.2%

0%

11.2%

Beaver Creek Gravity Sewer

100.0%

0%

0%

0%

Beaver Creek Gravity Sewer Land

100.0%

0%

0%

0%

Beaver Creek Trunk Sewer and Tunnel

50.0%

43.8%

0%

6.2%

Beaver Creek Trunk Sewer and Tunnel Land

50.0%

43.8%

0%

6.2%

Beaver Creek PS

21.3%

69.0%

0%

9.7%

Beaver Creek Force Main

21.3%

69.0%

0%

9.7%

Beaver Creek Force Main Land

34.7%

57.2%

0%

8.1%

Western Wake WRF

34.1%

57.7%

0%

8.2%

Effluent PS, Pipeline and Outfall Design

25.6%

43.4%

24.8%

6.2%

Effluent Pump Station

25.6%

43.4%

24.8%

6.2%

Effluent Pipeline and Outfall

26.9%

44.3%

22.5%

6.3%

Effluent Pipeline and Outfall Land

26.9%

44.3%

22.5%

6.3%

Holly Springs Effluent Line on WRF Site

0%

0%

100.0%

0%

Operating Budget

Project Management(Fixed Current Expenses)

26.7%

59.6%

5.3%

8.4%

Additional Items

SCADA

25.6%

43.4%

24.8%

6.2%

Value Engineering

25.6%

43.4%

24.8%

6.2%

Apex/Site 14 W/S Extension Policy (Option 1)

26.9%

44.3%

22.5%

6.3%

 

Table 2

Updated Budget for Preliminary Work

 

 

Permitting (Cary Project SW 1109)

 

Costs presented in March 2008 (PAC08-23)

$5,169,330

 

 

Additional permitting costs for current tasks

$100,000

CDM/CH2M Hill (preparing EIS with USACE direction)

 

Brown and Caldwell (Partners’ EIS Consultant)

 

Poyner and Spruill (legal review)

 

 

 

Additional budget for Harris Lake discharge evaluation and permitting

$200,000

 

 

Recommended Contingency

$230,670

Total costs for budget planning purposes

$5,700,000

 

 

Amount spent that was reimbursed by SRF loan

$1,430,214

 

 

Total of SRF loan payments (11/01/2007 – 05/01/2027)

$1,771,842

Total estimated costs not funded by SRF Loan

$4,269,786

Total payments for budget planning purposes

$6,041,628

 

 

Amount paid by Partners through 02/18/09 (including loan pmt)

$2,468,885

Estimated additional FY09 payments

$816,879

Remaining Budget Amount for FY10 and later

$2,755,864

 

 

 

 

Organizational, Institutional, Financial (Cary Project SW1113)

$600,000

(Amount spent through 2/18/09)

$67,320

 

 

 

 

Total Preliminary Work budget (SW1109 and SW1113)

$6,300,000


Table 3     Phase 1 Project Component Costs

 

Total Updated Project Costs (either actual spent or 2009 $)

 

 

 

Facility (design basis)

Engineering Costs

Construction Costs

Land costs

Subtotal Eng & Const Costs (2009 $)

Total Updated Costs

Mar 2008 costs

Increase (Decrease)

West Cary PS (peak hourly)

$1,217,111

$15,208,000

$318,000

$16,425,111

$16,743,111

$14,726,111

$2,017,000

14%

West Cary Force Main (peak hourly)

$743,376

$8,690,000

$509,800

$9,433,376

$9,943,176

$11,602,976

($1,659,800)

-14%

West Reedy Branch Gravity Sewer (peak hourly)

$866,675

$11,125,000

$312,500

$11,991,675

$12,304,175

$11,357,175

$947,000

8%

Beaver Creek Gravity Sewer

$23,890

$1,971,110

$70,000

$1,995,000

$2,065,000

 

$253,110

 

Beaver Creek Trunk Sewer and Tunnel

$0

$4,734,500

$65,500

$4,734,500

$4,800,000

 

$125,000

 

Beaver Creek PS (peak hourly)

$769,450

$18,517,400

$680,000

$19,286,850

$19,966,850

$18,035,950

$1,930,900

11%

Beaver Creek Force Main (peak hourly)

$1,068,287

$25,680,000

$743,700

$26,748,287

$27,491,987

$26,668,987

$823,000

3%

subtotal raw ww conveyance

$4,688,789

$85,926,010

$2,699,500

$90,614,799

$93,314,299

$82,391,199

$4,436,210

5%

Western Wake WRF (maximum month)

$10,826,000

$142,157,000

$7,585,000

$152,983,000

$160,568,000

$148,411,000

$12,157,000

8%

Effluent Pump Station (maximum month)

$1,002,560

$9,600,000

$1,235,000

$10,602,560

$11,837,560

$10,837,560

$1,000,000

9%

Effluent Pipeline and Outfall (maximum month)

$1,203,960

$39,605,000

$1,464,900

$40,808,960

$42,273,860

$39,149,080

$3,124,780

8%

Holly Springs Effluent Line on WRF site

$73,300

$862,000

$0

$935,300

$935,300

 

$107,000

 

subtotal effluent conveyance

$2,279,820

$50,067,000

$2,699,900

$52,346,820

$55,046,720

$49,986,640

$4,231,780

8%

SCADA 1

$1,100,000

$0

$0

$1,100,000

$1,100,000

$1,250,007

($150,007)

-12%

Value Engineering 1

$292,000

$0

$0

$292,000

$292,000

 

$0

 

SUBTOTAL

$19,186,609

$278,150,010

$12,984,400

$297,336,619

$310,321,019

$282,038,846

$20,674,983

7%

Water and Sewer Extension Policy 2

$270,600

$2,706,000

$250,000

$2,976,600

$3,226,600

$3,000,000

$226,600

 

TOTAL

$19,457,209

$280,856,010

$13,234,400

$300,313,219

$313,547,619

$285,038,846

$20,901,583

7%

1 SCADA costs allocated according to EPS design/construction cost allocation
2 Costs allocated according to preliminary work (permitting) cost allocation

 


Table 4

 

Updated Allocation of Western Wake Regional Wastewater Management Facilities By Project Partner

 

Preliminary Work (Permitting, Organizational, Institutional)

Apex

Cary

Holly Springs

Morrisville

Total

 

26.9%

44.3%

22.5%

6.3%

 

Costs in ILA (amended)

$704,000

$1,159,300

$588,800

$164,900

$2,617,000

Costs from Mar 2008 update (PAC08-23)

$1,482,400

$2,441,400

$1,240,000

$347,200

$5,510,958

Updated Preliminary Work Costs

$1,625,200

$2,676,400

$1,359,400

$380,600

$6,041,628

 

 

 

 

 

 

Increase (Decrease) from Mar 2008

$142,800

$235,000

$119,400

$33,400

$530,670

%

10%

10%

10%

10%

10%

Facilities and Land

 

 

 

 

 

Costs in ILA

$62,363,000

$137,425,000

$12,341,000

$19,386,000

$231,515,000

Costs from Mar 2008 update (PAC08-23)

$79,216,658

$173,007,988

$12,626,271

$24,562,676

$289,413,593

 

 

 

 

 

 

Updated Facility Costs (excluding land)

$81,498,381

$177,534,355

$13,091,967

$25,211,917

$297,336,619

Updated Land Costs

$3,988,167

$7,346,421

$607,478

$1,042,334

$12,984,400

Updated Facility and Land Costs

$85,486,548

$184,880,776

$13,699,444

$26,254,251

$310,321,019

 

 

 

 

 

 

Increase (Decrease) from Mar 2008

$6,269,890

$11,872,787

$1,073,173

$1,691,575

$20,907,426

%

8%

7%

8%

7%

7%

Total Preliminary Work, Facilities and Land Costs

 

 

 

 

 

Costs in ILA

$63,067,000

$138,584,300

$12,929,800

$19,550,900

$234,132,000

Costs from Mar 2008 update (PAC08-23)

$80,699,058

$175,449,388

$13,866,271

$24,909,876

$294,924,593

Updated Costs

$87,111,748

$187,557,176

$15,058,844

$26,634,851

$316,362,619

 

 

 

 

 

 

Increase (Decrease) from Mar 2008

$6,412,690

$12,107,787

$1,192,573

$1,724,975

$21,438,026

%

8%

7%

9%

7%

7%

Apex/Site 14 Water and Sewer Extension Policy

 $    867,955

 $     1,429,384

 $       725,985

 $    203,276

 $     3,226,600

Total Costs

Apex

Cary

Holly Springs

Morrisville

Total

Total Costs from Mar 2008 update (PAC08-23)

$81,506,058

$176,778,388

$14,541,271

$25,098,876

$297,924,593

Updated Total

$87,979,703

$188,986,560

$15,784,829

$26,838,127

$319,589,219

 

 

 

 

 

 

Increase (Decrease) from Mar 2008

$6,473,645

$12,208,171

$1,243,558

$1,739,251

$21,664,626

%

8%

7%

9%

7%

7%


Table 5

 

Western Wake Regional Wastewater Management Facilities Phase 1 Implementation

 

Estimated Cash Flow by Fiscal Year for Each Project Partner

 

Fiscal Year

Apex

Cary

Holly Springs

Morrisville

Total

Cary + Morrisville

Through FY09

 $   5,528,200

 $   14,727,300

 $  1,490,900

 $   2,079,300

 $   23,825,700

 $           16,806,600

FY10

 $   9,396,200

 $   16,408,300

 $     605,400

 $   2,331,900

 $   28,741,800

 $           18,740,200

FY11

 $ 28,557,200

 $   57,433,500

 $  2,985,600

 $   8,172,900

 $   97,149,200

 $           65,606,400

FY12

 $ 36,865,300

 $   83,194,700

 $  8,488,400

 $ 11,818,600

 $ 140,367,000

 $           95,013,300

FY13

 $   7,049,100

 $   16,249,700

 $  1,921,800

 $   2,296,400

 $   27,517,000

 $           18,546,100

FY14

 $        75,700

 $        138,800

 $       25,000

 $        19,800

 $        259,300

 $                158,600

FY15

 $        74,400

 $        136,400

 $       24,600

 $        19,500

 $        254,900

 $                155,900

FY16

 $        73,100

 $        134,100

 $       24,100

 $        19,100

 $        250,400

 $                153,200

FY17

 $        98,800

 $        176,100

 $       46,200

 $        25,100

 $        346,200

 $                201,200

FY18

 $        97,500

 $        173,700

 $       45,800

 $        24,800

 $        341,800

 $                198,500

FY19

 $        96,200

 $        171,400

 $       45,400

 $        24,400

 $        337,400

 $                195,800

FY20

 $        68,000

 $        124,800

 $       22,500

 $        17,800

 $        233,100

 $                142,600

FY21

 $        66,800

 $        122,400

 $       22,000

 $        17,500

 $        228,700

 $                139,900

FY22

 $        65,500

 $        120,100

 $       21,600

 $        17,100

 $        224,300

 $                137,200

FY23

 $        64,200

 $        117,700

 $       21,200

 $        16,800

 $        219,900

 $                134,500

FY24

 $        62,900

 $        115,400

 $       20,800

 $        16,500

 $        215,600

 $                131,900

FY25

 $        61,700

 $        113,100

 $       20,400

 $        16,100

 $        211,300

 $                129,200

FY26

 $        60,400

 $        110,700

 $       19,900

 $        15,800

 $        206,800

 $                126,500

FY27

 $        59,100

 $        108,400

 $       19,500

 $        15,500

 $        202,500

 $                123,900

TOTAL

 $ 88,420,300

 $ 189,876,600

 $15,871,100

 $ 26,964,900

 $ 321,132,900

 $         216,841,500

Notes:

 

1.  Includes loan payments for $4M Planning and Permitting SRF Loan

 

2.  Includes O&M costs through FY12, up until startup

 

3.  O&M costs for FY13 and later are not included

 

 

 

Table 6

Proposed FY09 Operating Budget

 

Total Cost

Spent Thru   2/18/09 1

Estimated Spent Thru Remainder of FY09 2

Proposed FY10   Operating Budget 2

 

Permitting

$6,041,628

$3,872,834

$4,715,978

$754,080

Organizational, Institutional, Financial

$600,000

$67,320

$67,320

$100,000

West Cary PS

$16,743,111

$5,326,048

$5,360,210

$52,027

West Cary Force Main

$9,943,176

$337,636

$429,190

$423,301

West Reedy Branch Gravity Sewer

$12,304,175

$420,758

$496,600

$292,815

Beaver Creek Gravity Sewer

$2,065,000

$21,501

$28,740

$49,358

Beaver Creek Trunk Sewer and Tunnel

$4,800,000

$0

$6,550

$45,850

Beaver Creek PS

$19,966,850

$412,612

$448,296

$735,649

Beaver Creek Force Main

$27,491,987

$501,170

$632,252

$611,746

Western Wake WRF

$160,568,000

$11,230,855

$11,808,029

$23,753,071

Effluent Pump Station

$11,837,560

$1,633,024

$1,670,527

$164,218

Effluent Pipeline and Outfall

$42,273,860

$546,509

$758,744

$1,133,627

Holly Springs Effluent Line on WRF Site

$935,300

$17,750

$23,305

$8,333

SCADA

$1,100,000

$317,086

$395,377

$117,437

Value Engineering

$292,000

$233,058

$262,529

$29,471

Apex/Site 14 Water / Sewer Extension Policy

$3,226,600

$0

$27,060

$290,590

SUBTOTAL

$320,189,247

$24,938,161

$27,130,707

$28,561,573

Operating Budget

Project Management

NA

$97,516

$196,000

$180,000

 TOTAL

$320,189,247

$25,035,677

$27,326,707

$28,741,573

1 Includes some funds reimbursed by, and payments that began in November 2007, for SRF loan of $3,958,770

 

 

 

 

 


 

< Back

2008 All Rights Reserved
Western Wake Partners

Home | About Us | Contact